High risk
  • Possession delayed ~12 yrs. Originally promised Jul 2023, now proposed Mar 2035 per the RERA filing.
Satellite view of this address

Where it is · Survey No-200 and Survey no-201, Poshir

Promoter

Builder profile

Builder
DOVE DEVELOPERS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000013360
Status
Ongoing
Stage
Certificate Signed
Possession
March 2035originally July 2023
Construction
18.2% complete
Units sold
1 of 41

Keep exploring

Where this project sits, who built it, and how Poshir compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.