The Gateway
CTS 784 784-1 786 788 792-A 793 785 787 791 848 790, Kurla, 400089
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · CTS 784 784-1 786 788 792-A 793 785 787 791 848 790, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Leafy eastern-suburb favourite with big redevelopment supply.
- Growth drivers:
- Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
- Who buys here:
- Eastern-suburb families upgrading within the area.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800024845
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 79.5% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.