Under construction
The Legend
MahaRERA P52100007333High risk
Sr.No2/2,3/2,3/1/1,3/1/2, Hinjawadi, 411057
Post your property hereOwn or renting out a unit in The Legend? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Hinjawadi come to you.
Oct 2021
Possession
18.2%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 18.2%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2021 per the RERA filing.
Satellite view of this address
Where it is · Sr.No2/2,3/2,3/1/1,3/1/2, Hinjawadi
Promoter
Builder profile
Shree Sankalp Associates
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100007333
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2021originally December 2020
- Construction
- 18.2% complete
- Units sold
- 0 of 0
Similar projects in Hinjawadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Blue Ridge Project C Land T18 and T19
Hinjawadi100% builtPoss. December 2018
YashONE Hinjawadi - Phase II
Hinjawadi100% builtPoss. March 2025
Blue Ridge - THE LOFTS
Hinjawadi99.2% builtPoss. December 20221 complaint
YashONE Hinjawadi - Phase 1
Hinjawadi99.2% builtPoss. December 2023
Rahul Aston - II
Hinjawadi96.8% builtPoss. December 20261 complaint
Megapolis Symphony Phase I
Hinjawadi90.9% builtPoss. July 20222 complaints
Yashwin SukhNiwas
Hinjawadi90.1% builtPoss. December 2024
Blueridge-The Groves
Hinjawadi90% builtPoss. June 2026
Keep exploring
Where this project sits, who built it, and how Hinjawadi compares.
In Hinjawadi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.