High risk
  • Litigation pending (6). MahaRERA's litigation disclosure lists 6 pending cases against this project.
  • 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 81.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.
Satellite view of this address

Where it is · F.P NO 36 AND 37 OF TPS II, GHATKOPAR

Area guide

What it's like to buy in GHATKOPAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Raveshia Realtors

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
YMS Consultants Limited

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900026208
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
81.4% complete
Units sold
44 of 147

Similar projects in GHATKOPAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how GHATKOPAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.