High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • 7 appeals at MahaREAT. 7 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Feb 2019, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · Srvy No-186, CTS No-1155P, 1156P, 1157P, WAKAD

Promoter

Builder profile

Builder
Vastukalp Promoters And Builders

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100001650
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally February 2019
Construction
81.8% complete
Units sold
0 of 0

Similar projects in WAKAD

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how WAKAD compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.