High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 2051 & 7, Vasai

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
TOPAZ HOMES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000011693
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
51.4% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.