High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 135 1+2B, Pune City

Promoter

Builder profile

Builder
GRUHA NAVNIRMAN HOUSING

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100046527
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
52.3% complete
Units sold
0 of 0

Similar projects in Pune City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pune City compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.