Under construction

TREELAND PHASE-5

MahaRERA P51600034430High risk

by ABH DEVELOPERS PRIVATE LIMITED

HISSA NO-5,6 AND 9, OF S NO 21/1 AND 3, 24, 25/1 AND 25/2, 167, 28/1/2/1, 28/1/2/2, AND 26/1, GANGAPUR ROAD, 422025

Official record
Apr 2027
Possession
63.6%
Built
0
Complaints
126
Units
High risk
  • Mortgaged to a lender (₹100 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹100 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · HISSA NO-5,6 AND 9, OF S NO 21/1 AND 3, 24, 25/1 AND 25/2, 167, 28/1/2/1, 28/1/2/2, AND 26/1, GANGAPUR ROAD

Area guide

What it's like to buy in GANGAPUR ROAD

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
ABH DEVELOPERS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
UMESH BAGUL

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51600034430
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2025
Construction
63.6% complete
Units sold
115 of 126

Similar projects in GANGAPUR ROAD

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how GANGAPUR ROAD compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.