Under construction

TRIDENT

MahaRERA P52100026732High risk

by DEU ASSOCIATES

Survey Nos. 16/33, 16/34, 16/35 and 16/36 at Village Pimple Nilakh, PIMPLE NILKH, 411027

Official record
May 2024
Possession
36.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2024) has passed with construction at 36.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2024 per the RERA filing.
Satellite view of this address

Where it is · Survey Nos. 16/33, 16/34, 16/35 and 16/36 at Village Pimple Nilakh, PIMPLE NILKH

Promoter

Builder profile

Builder
DEU ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100026732
Status
New
Stage
Certificate Signed
Possession
May 2024
Construction
36.4% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how PIMPLE NILKH compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.