High risk
  • Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Oct 2019) has passed with construction at 59.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2019 per the RERA filing.
Satellite view of this address

Where it is · S NO 169 HISSA 3 - 7, Pimpri Chinchawad (M Corp.)

Promoter

Builder profile

Builder
Om Developers Project Green

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100005869
Status
Ongoing
Stage
Certificate Signed
Possession
October 2019originally October 2018
Construction
59.5% complete
Units sold
0 of 0

Similar projects in Pimpri Chinchawad (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pimpri Chinchawad (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.