Under construction
TULIP SWAPNALOK
MahaRERA P52100011375High risk
660,661,662,663,666 AT MOSHI, Pimpri Chinchawad (M Corp.), 412105
Post your property hereOwn or renting out a unit in TULIP SWAPNALOK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Pimpri Chinchawad (M Corp.) come to you.
Oct 2020
Possession
90.9%
Built
2
Complaints
0
Units
High risk
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~3 yrs. Originally promised Dec 2017, now proposed Oct 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.
Satellite view of this address
Where it is · 660,661,662,663,666 AT MOSHI, Pimpri Chinchawad (M Corp.)
Promoter
Builder profile
Tulip Properties
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100011375
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2020originally December 2017
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Pimpri Chinchawad (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mahindra Citadel - Phase 5
Pimpri Chinchawad (M Corp.)Poss. December 2031
PAVAN
Pimpri Chinchawad (M Corp.)Poss. January 2028
MANTRA MOMENTS PHASE 2
Pimpri Chinchawad (M Corp.)100% builtPoss. December 20182 complaints
SILVERLAND RESIDENCY PHASE-1
Pimpri Chinchawad (M Corp.)100% builtPoss. December 2021
Mantra Moments Phase 4
Pimpri Chinchawad (M Corp.)100% builtPoss. November 20191 complaint
GLITTERATI II
Pimpri Chinchawad (M Corp.)100% builtPoss. April 2018
Mantra Moments Phase 3
Pimpri Chinchawad (M Corp.)100% builtPoss. June 2018
Svasti Chandrasuman
Pimpri Chinchawad (M Corp.)100% builtPoss. August 2019
Keep exploring
Where this project sits, who built it, and how Pimpri Chinchawad (M Corp.) compares.
In Pimpri Chinchawad (M Corp.)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.