- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Where it is · S.NO 41 H.NO 1/1A, Vasai
Area guide
What it's like to buy in Vasai
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The western line's volume market — dense affordable towers past Mira Road.
- Growth drivers:
- Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
- Who buys here:
- Budget-first buyers who commute the western line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000016287
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Vasai
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Vasai compares.
In Vasai
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.