Under construction

Tulsidas City Center

MahaRERA P52100078760High risk

by Rythm Properties

PLOT NO. 243 CTS No. 2604, Near Shagun Chowk, 411017

Official record
Dec 2025
Possession
40.9%
Built
0
Complaints
20
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 40.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO. 243 CTS No. 2604, Near Shagun Chowk

Area guide

What it's like to buy in Near Shagun Chowk

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Rythm Properties

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Nishita Naik

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100078760
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
40.9% complete
Units sold
0 of 20

Keep exploring

Where this project sits, who built it, and how Near Shagun Chowk compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.