Under construction

TUNGABHADRA CO OP HSG SOC

MahaRERA P52100046370High risk

by Unknown

S.N. 89&90, PLOT NO 40, Haveli, 411038

Official record
Aug 2026
Possession
81.8%
Built
0
Complaints
40
Units
High risk
  • Possession delayed ~1 yr. Originally promised Apr 2025, now proposed Aug 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2026) has passed with construction at 81.8%.
Satellite view of this address

Where it is · S.N. 89&90, PLOT NO 40, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Unknown

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100046370
Status
New
Stage
Certificate Signed
Possession
August 2026originally April 2025
Construction
81.8% complete
Units sold
9 of 40

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 8 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.