TYCOONS ORBIS
Survey Number 35 Hissa Number 1, Kalyan, 421301
- Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 44.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · Survey Number 35 Hissa Number 1, Kalyan
Area guide
What it's like to buy in Kalyan
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central-line volume market — affordable towers around busy junctions.
- Growth drivers:
- Metro 5, ring-road plans, the region's most accessible pricing.
- Who buys here:
- Budget-first buyers who commute the central line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700020227
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2023
- Construction
- 44.4% complete
- Units sold
- 98 of 333
Similar projects in Kalyan
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kalyan compares.
In Kalyan
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.