High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~5 yrs. Originally promised Jul 2022, now proposed Dec 2027 per the RERA filing.
  • 17 RERA complaints. 17 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 13-PT, Near Bhivpuri Railway Station

Promoter

Builder profile

Builder
Udaan Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000008827
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally July 2022
Construction
58.5% complete
Units sold
0 of 0