High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Jul 2027 per the RERA filing.
  • Behind schedule. Possession is due Jul 2027 but construction is only at 41.8%.
Satellite view of this address

Where it is · CTS NO 894, Pune City

Promoter

Builder profile

Builder
PRIME PRIORITIES UNIT 1

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100045837
Status
New
Stage
Certificate Signed
Possession
July 2027originally March 2024
Construction
41.8% complete
Units sold
0 of 0

Similar projects in Pune City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pune City compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.