High risk
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 99.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO. 125, SECTOR 48, NA

Promoter

Builder profile

Builder
MURUDESHWAR DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000002083
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally June 2021
Construction
99.8% complete
Units sold
0 of 0