High risk
  • Possession delayed ~4 yrs. Originally promised Apr 2026, now proposed Apr 2030 per the RERA filing.
Satellite view of this address

Where it is · 10/1/8/1, Haveli

Promoter

Builder profile

Builder
Mayuresh Constructions

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Nilesh saswade

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100028216
Status
New
Stage
Certificate Signed
Possession
April 2030originally April 2026
Construction
62.3% complete
Units sold
14 of 44

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.