42.3%
Built
0
Complaints
166
Units
High risk
  • Mortgaged to a lender (₹10 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹10 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Behind schedule. Possession is due Aug 2027 but construction is only at 42.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2027 per the RERA filing.
Satellite view of this address

Where it is · New SNo 288, Hno C/1, Old Sno 288, Hno A/1/2/A, VIRAR

Area guide

What it's like to buy in VIRAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
VARDHAMAN HOUSING

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
HIMESH GUPTA & ASSOCIATES VIJAY GUPTA

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P99000055914
Status
New
Stage
Certificate Signed
Possession
August 2027
Construction
42.3% complete
Units sold
50 of 166

Similar projects in VIRAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how VIRAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.