High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2019, now proposed Jan 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 51.5%.
Satellite view of this address

Where it is · 52/9, Tambe Wasti

Promoter

Builder profile

Builder
Girijapati Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100004861
Status
Ongoing
Stage
Certificate Signed
Possession
January 2021originally July 2019
Construction
51.5% complete
Units sold
0 of 0