Under construction

USHA KIRAN RESIDENCY F1 F2

MahaRERA P51700004142High risk

by STALWART IMPEX PVT LTD

S NO 3 HISSA NO 2 3 4 5 7 P 8 9 10, Ambarnath, 421503

Official record
Jul 2026
Possession
90.9%
Built
0
Complaints
187
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 90.9%.
Satellite view of this address

Where it is · S NO 3 HISSA NO 2 3 4 5 7 P 8 9 10, Ambarnath

Area guide

What it's like to buy in Ambarnath

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
STALWART IMPEX PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700004142
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026originally December 2018
Construction
90.9% complete
Units sold
110 of 187

Similar projects in Ambarnath

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ambarnath compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.