Under construction
V M HERITAGE 2
MahaRERA P52000011478High risk
CTS 1048 SURVEY42/4, Khopoli, 410203
Post your property hereOwn or renting out a unit in V M HERITAGE 2? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Khopoli come to you.
Jan 2020
Possession
33.6%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jan 2020) has passed with construction at 33.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2020 per the RERA filing.
Satellite view of this address
Where it is · CTS 1048 SURVEY42/4, Khopoli
Promoter
Builder profile
DILAWAR SUJATKHAN PATHAN
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000011478
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- January 2020originally July 2019
- Construction
- 33.6% complete
- Units sold
- 0 of 0
Similar projects in Khopoli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
City Of Music Phase III
KhopoliPoss. December 20261 complaint
BRIGHT ENCLAVE
KhopoliPoss. December 2026
Murlidhar Homes Phase 1
KhopoliPoss. December 2030
Ashiyana Infinity
KhopoliPoss. December 2032
ALIANA CITY PLAZA PHASE II
Khopoli100% builtPoss. March 2022
NADMOHAN
Khopoli90.9% builtPoss. December 2018
Madhav Ashirwad
Khopoli90.9% builtPoss. January 2021
Chishti Apartment
Khopoli90.9% builtPoss. December 2019
Keep exploring
Where this project sits, who built it, and how Khopoli compares.
In Khopoli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.