Under construction

VAIBHAV CHOWK SRA CHS LTD

MahaRERA P51800015339High risk

by SUNIL MOHAN JOSHI

CTS NO 60 1-70 BHANDUP VILLAGE, BHANDUP WEST, 400078

Official record
Dec 2026
Possession
3.6%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 3.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · CTS NO 60 1-70 BHANDUP VILLAGE, BHANDUP WEST

Area guide

What it's like to buy in BHANDUP WEST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SUNIL MOHAN JOSHI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800015339
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2022
Construction
3.6% complete
Units sold
0 of 0

Similar projects in BHANDUP WEST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how BHANDUP WEST compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.