High risk
  • Possession delayed ~5 yrs. Originally promised Jul 2022, now proposed Mar 2027 per the RERA filing.
Satellite view of this address

Where it is · 61-3 VILLAGE LADIVALI, LADIWALI

Area guide

What it's like to buy in LADIWALI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AVDHOOT REALITY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000019588
Status
New
Stage
Certificate Signed
Possession
March 2027originally July 2022
Construction
90.9% complete
Units sold
19 of 23