Under construction

Vallabh Co-op Housing Society

MahaRERA P52100050438High risk

by SRKD LANDMARK LLP

CTS NO. 968+969, FINAL PLOT NO. 395+396, PLOT NO. 38+39, SHIVAJI NAGAR-BHAMBURDA, Bhamburda, 411016

Official record
Sept 2026
Possession
63.6%
Built
0
Complaints
33
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Sept 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Promoter

Builder profile

Builder
SRKD LANDMARK LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Devendra V Dhere

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100050438
Status
New
Stage
Certificate Signed
Possession
September 2026originally March 2025
Construction
63.6% complete
Units sold
16 of 33