High risk
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2020 per the RERA filing.
Satellite view of this address

Where it is · PLOT 2 /3, Varale

Promoter

Builder profile

Builder
CHRISHH OMKARA CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100005792
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020
Construction
90.9% complete
Units sold
0 of 0