Under construction
VASTU HERITAGE
MahaRERA P51700048963High risk
SURVEY NO 24,HISSA NO 3,SURVEY NO 23,HISSA NO.1 & 2, THAKURLI, 421201
Post your property hereOwn or renting out a unit in VASTU HERITAGE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in THAKURLI come to you.
Dec 2026
Possession
23.6%
Built
0
Complaints
23
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 23.6%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Area guide
What it's like to buy in THAKURLI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
MINAKSHI DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700048963
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 23.6% complete
- Units sold
- 12 of 23
Similar projects in THAKURLI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
ADITYA DARSHAN CHS
THAKURLIPoss. March 2031
JAI SANTOSHI MATA HEIGHTS
THAKURLI100% builtPoss. September 2018
KRITIJA ENCLAVE
THAKURLI40.9% builtPoss. June 2027
Keep exploring
Where this project sits, who built it, and how THAKURLI compares.
In THAKURLI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.