Caution
  • Behind schedule. Possession is due Jul 2027 but construction is only at 39.4%.
Satellite view of this address

Where it is · 209/1/A/4, Baramati (M Cl)

Promoter

Builder profile

Builder
M/S BARGE AND GOLE CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100004405
Status
Ongoing
Stage
Certificate Signed
Possession
July 2027
Construction
39.4% complete
Units sold
0 of 0