Jul 2027
Possession
39.4%
Built
0
Complaints
0
Units
Caution
- Behind schedule. Possession is due Jul 2027 but construction is only at 39.4%.
Satellite view of this address
Where it is · 209/1/A/4, Baramati (M Cl)
Promoter
Builder profile
M/S BARGE AND GOLE CONSTRUCTION
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100004405
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2027
- Construction
- 39.4% complete
- Units sold
- 0 of 0
Similar projects in Baramati (M Cl)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHINDE PARK
Baramati (M Cl)Poss. August 2018
KRUPASINDHU CLASSIC
Baramati (M Cl)Poss. October 2027
Renuka Pride
Baramati (M Cl)100% builtPoss. December 2017
SAIDHAM
Baramati (M Cl)90.9% builtPoss. October 2021
PANDURANG PRESTIGE POINT PHASE 1
Baramati (M Cl)90.9% builtPoss. January 2019
SAI SADAN RESIDENCY 1
Baramati (M Cl)90.9% builtPoss. June 2019
CHINTAMANI COMPLEX
Baramati (M Cl)90.9% builtPoss. December 2018
SANSKRUTI RESIDENCY
Baramati (M Cl)90.9% builtPoss. January 2021
Keep exploring
Where this project sits, who built it, and how Baramati (M Cl) compares.
In Baramati (M Cl)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.