Caution
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 55.9%.
Satellite view of this address

Where it is · 923, CHIKHALI

Promoter

Builder profile

Builder
maheshdada devlopers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100014728
Status
New
Stage
Certificate Signed
Possession
December 2021
Construction
55.9% complete
Units sold
5 of 20

Similar projects in CHIKHALI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how CHIKHALI compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.