High risk
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 55%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2025 per the RERA filing.

Area guide

What it's like to buy in Kandivali west

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
V.D. Infratech Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800029400
Status
New
Stage
Certificate Signed
Possession
June 2025originally December 2024
Construction
55% complete
Units sold
174 of 176

Similar projects in Kandivali west

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kandivali west compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.