Post your property hereOwn or renting out a unit in Venkatesh Pushpakala? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Saswad come to you.
Dec 2026
Possession
1.5%
Built
0
Complaints
44
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 1.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Area guide
What it's like to buy in Saswad
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SANJAY DNYNOBA JAGTAP
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100020045
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 1.5% complete
- Units sold
- 44 of 44
Similar projects in Saswad
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
NANDANVAN
SaswadPoss. October 2019
ANUGRAH
SaswadPoss. December 2028
Balaji Paradise
SaswadPoss. April 20311 complaint
SHREENIWAS
Saswad100% builtPoss. March 2021
UDYAM BIZBAY
Saswad90.9% builtPoss. June 2023
NB Coral
Saswad88.2% builtPoss. September 2023
SHIVSHAMBHO RESIDENCY II
Saswad84.1% builtPoss. June 2023
UDYAM BIZ CASA
Saswad81.8% builtPoss. September 2024
Keep exploring
Where this project sits, who built it, and how Saswad compares.
In Saswad
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.