Under construction
VERISTA
MahaRERA P52100047130High risk
Final Plot 83/10,CTS 124/10, Off Law College Road, Erandwane, Erandwane, 411004
Post your property hereOwn or renting out a unit in VERISTA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Erandwane come to you.
May 2025
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (May 2025) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2025 per the RERA filing.
Satellite view of this address
Where it is · Final Plot 83/10,CTS 124/10, Off Law College Road, Erandwane, Erandwane
Promoter
Builder profile
VM REAL TECH LLP
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100047130
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Erandwane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
PASAYADAN SRUSHTI
ErandwanePoss. December 2027
Swapna Samrajya Co-oprative Housing Society Limited
ErandwanePoss. December 2031
Veena Apartment Condominium
ErandwanePoss. June 2027
Prabhat Garima
ErandwanePoss. April 2029
Triveni Co-operative Housing Society Ltd PH 2
ErandwanePoss. December 2028
APOORVA APARTMENT CONDOMINIUM
ErandwanePoss. October 2028
Purti Apartments Condominium
ErandwanePoss. June 2028
Sonali Society
ErandwanePoss. November 2027
Keep exploring
Where this project sits, who built it, and how Erandwane compares.
In Erandwane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.