High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No 242, Hissa No 7, Kalyan

Promoter

Builder profile

Builder
Versatile Corporation

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700007989
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2025
Construction
63.6% complete
Units sold
0 of 0

Similar projects in Kalyan

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kalyan compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.