Under construction

VERTICA PHASE 2

MahaRERA P52100034995High risk

by V Realty

SR NO 23/3/1/3 23/3/1/6 23/3/1/7 23/3/4 23/3/3 P 23/3/1/8 23/3/1/2 23/3/1/1 23/3/5/1 23/5/1/22 23/4A/1/9 23/4A/1/7 23/3/5/3 23/3/5B 23/3/1/5 23/3/1/4 23/5/1/13 23/5/1/30 23/4A/1/8 23/4A/19 23/3/2 23/5/10 23/3/1 23/3/6 23/5/11 23/5/12 23/5/1/33, BALEWADI, 411045

Official record
Apr 2029
Possession
45.3%
Built
0
Complaints
46
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2026, now proposed Apr 2029 per the RERA filing.
Satellite view of this address

Where it is · SR NO 23/3/1/3 23/3/1/6 23/3/1/7 23/3/4 23/3/3 P 23/3/1/8 23/3/1/2 23/3/1/1 23/3/5/1 23/5/1/22 23/4A/1/9 23/4A/1/7 23/3/5/3 23/3/5B 23/3/1/5 23/3/1/4 23/5/1/13 23/5/1/30 23/4A/1/8 23/4A/19 23/3/2 23/5/10 23/3/1 23/3/6 23/5/11 23/5/12 23/5/1/33, BALEWADI

Area guide

What it's like to buy in BALEWADI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
V Realty

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
ANA CONSORTIUM PVT LTD

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100034995
Status
New
Stage
Certificate Signed
Possession
April 2029originally March 2026
Construction
45.3% complete
Units sold
12 of 46

Similar projects in BALEWADI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how BALEWADI compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.