Under construction
Vertical Oriana Phase III
MahaRERA P52100005269High risk
Survey No7/1A 2A 2B, Mundhwa, 411036
Post your property hereOwn or renting out a unit in Vertical Oriana Phase III? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mundhwa come to you.
Dec 2021
Possession
51.1%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 51.1%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2021 per the RERA filing.
Area guide
What it's like to buy in Mundhwa
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Vertical Infra
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100005269
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally January 2021
- Construction
- 51.1% complete
- Units sold
- 0 of 0
Similar projects in Mundhwa
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Indeco Tech Park
MundhwaPoss. March 2030
Godrej Skyline
MundhwaPoss. July 20291 complaint
Kumar Prism Tower A
MundhwaPoss. December 2031
Element Square
MundhwaPoss. December 2029
Ace Abundance
MundhwaPoss. March 2030
MEDIA CLASSIC
MundhwaPoss. August 2028
Eleve 1
MundhwaPoss. March 2029
Anandtara Iris Residences Phase III
MundhwaPoss. June 2029
Keep exploring
Where this project sits, who built it, and how Mundhwa compares.
In Mundhwa
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.