High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 49.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.

Area guide

What it's like to buy in SECTOR R5

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NOOR MOHAMMED IDRIS JALGAONKAR

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000027308
Status
New
Stage
Certificate Signed
Possession
June 2023originally June 2022
Construction
49.8% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how SECTOR R5, PUSHPAK NAGAR, NAVI MUMBAI compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.