High risk
  • Possession date passed. The proposed possession date (Aug 2022) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2022 per the RERA filing.

Promoter

Builder profile

Builder
Varsha Naresh Lalwani

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000022469
Status
New
Stage
Certificate Signed
Possession
August 2022
Construction
0% complete
Units sold
0 of 0