Vihang Woods
91/1/1A,2A,102/1,2B,2C,3B,103/1,2,3A,4,5B/2,104/7B,7C,8B,11B, 109/29B,30/B,30/4A,33,34, Thane, 400615
- Litigation pending (7). MahaRERA's litigation disclosure lists 7 pending cases against this project.
- Behind schedule. Possession is due Apr 2027 but construction is only at 37%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Where it is · 91/1/1A,2A,102/1,2B,2C,3B,103/1,2,3A,4,5B/2,104/7B,7C,8B,11B, 109/29B,30/B,30/4A,33,34, Thane
Area guide
What it's like to buy in Thane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700005038
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2026
- Construction
- 37% complete
- Units sold
- 55 of 59
Similar projects in Thane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Thane compares.
In Thane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.