- Possession delayed ~5 yrs. Originally promised Dec 2018, now proposed Jun 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 90.9%.
Where it is · 23 PLOT 1, Nashik (M Corp.)
Area guide
What it's like to buy in Nashik (M Corp.)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Office corridors (SEEPZ, MIDC) with value housing pockets between them.
- Growth drivers:
- Airport proximity, Metro 1/7, IT-park employment.
- Who buys here:
- Working couples prioritising commute over frills.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600012034
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2024originally December 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Nashik (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Nashik (M Corp.) compares.
In Nashik (M Corp.)
The developer
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.