High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 27.3%.
Satellite view of this address

Where it is · S.n. 330/1 to 7/2/3/12, Samarth nagar

Promoter

Builder profile

Builder
RAMESHWAR ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600032672
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
27.3% complete
Units sold
0 of 0