High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 79.8%.
  • Promised amenities not started. Swimming Pool, Landscaped Garden are at 0% build with possession due Jun 2023 per the RERA filing.
Satellite view of this address

Where it is · Survey No 45 P and 46 P, mhalunge

Area guide

What it's like to buy in mhalunge

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NNP BUILDCON PVT. LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100007943
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally June 2022
Construction
79.8% complete
Units sold