Vtp Cygnus- Nation R1-Tower7
by Ashdan Developers Private Limited
Gat Nos. 155, 156, 157, 158, Manjri, 412307
- Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
- 10 appeals at MahaREAT. 10 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~2 yrs. Originally promised Jul 2021, now proposed Jan 2023 per the RERA filing.
- 40 RERA complaints. 40 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Jan 2023) has passed with construction at 90.9%.
Where it is · Gat Nos. 155, 156, 157, 158, Manjri
Area guide
What it's like to buy in Manjri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100009524
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- January 2023originally July 2021
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Manjri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Manjri compares.
In Manjri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.