High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~5 yrs. Originally promised Dec 2022, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · 1589, Bhiwandi

Promoter

Builder profile

Builder
WADHWA BUILDCON LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700007370
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2022
Construction
4.5% complete
Units sold
0 of 0

Similar projects in Bhiwandi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Bhiwandi compares.

Data sourced from the official MahaRERA portal; complaints last synced 5 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.