Under construction

WEST AVENUE

MahaRERA P52100016725High risk

by RAINBOW CONSTRUCTIONS

S.NO2 H.NO 2B,3A,3B , CTS NO 2561 PART , AUNDH, PANDI BHIMSEN KALAMANDIR, 411067

Official record
Aug 2023
Possession
38%
Built
0
Complaints
184
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 38%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2023 per the RERA filing.
Satellite view of this address

Where it is · S.NO2 H.NO 2B,3A,3B , CTS NO 2561 PART , AUNDH, PANDI BHIMSEN KALAMANDIR

Area guide

What it's like to buy in PANDI BHIMSEN KALAMANDIR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
RAINBOW CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Hirak - Shah

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100016725
Status
New
Stage
Certificate Signed
Possession
August 2023originally February 2023
Construction
38% complete
Units sold
165 of 184

Keep exploring

Where this project sits, who built it, and how PANDI BHIMSEN KALAMANDIR compares.