WEST AVENUE
S.NO2 H.NO 2B,3A,3B , CTS NO 2561 PART , AUNDH, PANDI BHIMSEN KALAMANDIR, 411067
- Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 38%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2023 per the RERA filing.
Where it is · S.NO2 H.NO 2B,3A,3B , CTS NO 2561 PART , AUNDH, PANDI BHIMSEN KALAMANDIR
Area guide
What it's like to buy in PANDI BHIMSEN KALAMANDIR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100016725
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2023originally February 2023
- Construction
- 38% complete
- Units sold
- 165 of 184
Keep exploring
Where this project sits, who built it, and how PANDI BHIMSEN KALAMANDIR compares.
In PANDI BHIMSEN KALAMANDIR
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.