High risk
  • Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project — the strongest enforcement action on record.
  • Possession delayed ~4 yrs. Originally promised Jun 2019, now proposed Feb 2023 per the RERA filing.
  • 33 RERA complaints. 33 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 174/C, Borivali

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Rajesh Real Estate Developers Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800007798
Status
Ongoing
Stage
Certificate Signed
Possession
February 2023originally June 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.