Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A2
by Wadhwa Construction and Infrastructure Private Limited
Survey No. 128/8, 128/9, Wadhwa Wise City, 410206
- Behind schedule. Possession is due Dec 2026 but construction is only at 28.5%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · Survey No. 128/8, 128/9, Wadhwa Wise City
Area guide
What it's like to buy in Wadhwa Wise City
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000021106
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 28.5% complete
- Units sold
- 0 of 0
Similar projects in Wadhwa Wise City
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Wadhwa Wise City compares.
In Wadhwa Wise City
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.