High risk
  • Possession delayed ~5 yrs. Originally promised Jun 2024, now proposed Apr 2029 per the RERA filing.
  • 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · S NO 105 1 PT AND 2 PT, VINAY NAGAR

Promoter

Builder profile

Builder
RAJDEEP REALTORS & DEVELOPERS PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Design Concept

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700028141
Status
New
Stage
Certificate Signed
Possession
April 2029originally June 2024
Construction
33.7% complete
Units sold
284 of 355

Similar projects in VINAY NAGAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how VINAY NAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 28 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.