Under construction

WOLLYWOOD PHASE II

MahaRERA P99000014632High risk

by NIRVANA LIFESTYLE VENTURES

Survey Numbers - 61 1,615,61 72,73 12, 73 21 Final Plot No. 1,2,24,25,26,28,31,32,33,34,35,36,37,40,87,88 & 89, Vada, 421303

Official record
Dec 2026
Possession
61.2%
Built
4
Complaints
25
Units
High risk
  • 3 appeals at MahaREAT. 3 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
  • High complaint rate. 4 complaints against only 24 sold units — a high rate for a project this size.
Satellite view of this address

Where it is · Survey Numbers - 61 1,615,61 72,73 12, 73 21 Final Plot No. 1,2,24,25,26,28,31,32,33,34,35,36,37,40,87,88 & 89, Vada

Area guide

What it's like to buy in Vada

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NIRVANA LIFESTYLE VENTURES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DEEPAK HIREMATH ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000014632
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2022
Construction
61.2% complete
Units sold
24 of 25

Similar projects in Vada

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vada compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.