WOLLYWOOD PHASE II
Survey Numbers - 61 1,615,61 72,73 12, 73 21 Final Plot No. 1,2,24,25,26,28,31,32,33,34,35,36,37,40,87,88 & 89, Vada, 421303
- 3 appeals at MahaREAT. 3 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- High complaint rate. 4 complaints against only 24 sold units — a high rate for a project this size.
Where it is · Survey Numbers - 61 1,615,61 72,73 12, 73 21 Final Plot No. 1,2,24,25,26,28,31,32,33,34,35,36,37,40,87,88 & 89, Vada
Area guide
What it's like to buy in Vada
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P99000014632
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 61.2% complete
- Units sold
- 24 of 25
Similar projects in Vada
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Vada compares.
In Vada
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.