Under construction
Wonderwall
MahaRERA P52100015766High risk
40/4/2/2, 40/4/2/3, 40/4/2/4, 40/4/2/6, 40/4/2/8, 40/4/2/9, Balewadi, 411045
Post your property hereOwn or renting out a unit in Wonderwall? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Balewadi come to you.
Jul 2019
Possession
64.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 64.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2019 per the RERA filing.
Satellite view of this address
Where it is · 40/4/2/2, 40/4/2/3, 40/4/2/4, 40/4/2/6, 40/4/2/8, 40/4/2/9, Balewadi
Promoter
Builder profile
Ashwin Ulhas Trimal
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100015766
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2019
- Construction
- 64.5% complete
- Units sold
- 0 of 0
Similar projects in Balewadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
KIMAYA ONE
BalewadiPoss. April 2030
Sai Canary A3
BalewadiPoss. April 2029
The Enclave
BalewadiPoss. April 2030
THE HAMPTONNS
BalewadiPoss. April 2031
Dream Velmore
BalewadiPoss. April 20331 complaint
MARQIS PHASE 1
BalewadiPoss. April 2030
Thorve House
BalewadiPoss. October 2027
SIGNIS
BalewadiPoss. March 2029
Keep exploring
Where this project sits, who built it, and how Balewadi compares.
In Balewadi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.